Skip to main content
District

Construction News

Construction News & Updates

 

Mukilteo Elementary School, originally built in 1982, is situated on 9.8 acres within the City of Mukilteo. The existing facility encompasses 41,727 square feet and includes ten portable classrooms. A comprehensive master plan for the school's complete replacement has been developed, outlining the scope of Phase I, which involves relocating these ten classrooms into a new, dedicated building.

Phase I will introduce a new building of approximately 19,973 square feet. This phase also includes significant site work, such as the development of a play area, walkways, fire lane enhancements, and landscaping improvements. Additionally, new utility services will feature a storm detention system to manage water runoff effectively. Construction is slated to commence in Summer 2024, with the project expected to reach completion by Fall 2025.

New Mukilteo Elementary Exterior

  • Construction work
  • Construction work
  • Construction work
  • Construction work
  • Construction work
  • Construction work
Virtual

Explore the Transformation: Virtual Tour of Current and New Mukilteo Elementary Facilities

Experience a virtual tour of both the current and upcoming buildings! The new building, which will be the initial phase of our expansion, will feature ten state-of-the-art classrooms designed to provide an inspiring learning environment for many enthusiastic students.

Explore, Now!
Virtual

A Sneak Peek into the Future: Exploring the New Mukilteo Elementary

Step through the doors of the new Mukilteo Elementary building and imagine the transformation coming in just one year. What you see in this virtual preview will soon become a reality! We’re excited to move into this new expansion and welcome a bright future.

Explore, Now!

Project Timeline

Excavators digging up a large rock

August 2024

  • The civil contractor removed a large boulder found underground while digging the storm retention vault. 
  • Media filters have been installed (storm vault) and covered over with crushed rock. 
  • Utility work continues onsite.
  • Hard surface area prep is underway in preparation for the start of school in September. 

July 2024

  • Site preparation and excavation is underway.
  • Electrical contractor is installing temporary utility lines to power construction site. 
  • Dirt work contractor is excavating storm retention on the north side of the site.  

June 2024

  • Permits issued by City of Mukilteo. 
  • Contractor kicked off construction on June 26.